Run Card for FlexFET process

 

 

Step 64. M1 photo   

 

 

 

Steps

Notes

Date

Operator

 

64.1

 

 

Standard DUV litho with BARC:

 

PM mark signals are very weak, need recovery:

-          Open up PM dies on every wafer

-          BARC etch in Centura: MXP_BARC_ETCH recipe, 40 sec

-          Wet etch Al in Sink8 until gone (~1min)

 

Note: F#2 required further treatment: Lam3 Al etch followed by MXP_OXSP_ETCH. Finally got aligned on 8/13/04 and further process completed on 8/16/04.

 

Ash and recoat wafers with BARC+UV210 resist

 

ASML:

-          Energy-focus matrix to determine best exposure settings

-          Expose every wafer with 32mJ at -1.1um focus offset

 

Hard bake: UVBAKE, pr.J

 

08/10/04

Horvath